ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 123

In which scenario would using the Copy Project action NOT result in a new project record being created?

Answer options

Correct answer: D

Explanation

The correct answer is D because copying partial projects does not create a new project record since the action is not intended for incomplete data. Options A, B, and C involve scenarios where complete projects or sub-projects are being copied, which would typically result in the creation of a new project record.