ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 117

If the ‘Move project for WIP projects’ property is enabled, project tasks associated with the project are also moved, except for tasks in which of the following states? (Choose two.)

Answer options

Correct answer: B, C

Explanation

The correct answers are B and C because tasks that are 'Closed' and 'Work in Progress' are not moved when the project is relocated. In contrast, tasks that are 'Pending' or 'Open' can be moved along with the project.