ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 115

Which of the following defines a parent-child relationship? (Choose two.)

Answer options

Correct answer: B, D

Explanation

Option B is correct because a parent-child relationship does not exist as a separate record in a database table but rather as a logical structure. Option D is also correct as it allows for the organization of multiple child tasks under one parent task, regardless of dependencies. Options A and C are incorrect; A is false because parent-child relationships can influence task scheduling, and C is incorrect since a parent task's completion does not necessarily dictate the start of another task.