ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 109

During the allocation process, when named resources are allocated to a plan, where is resource cost derived from?

Answer options

Correct answer: A

Explanation

The correct answer is A because the cost for the resource is derived from the labor rate card associated with the specific user. The other options do not accurately reflect the direct cost source as they refer to broader periods or different records that aren't specifically tied to the individual user.