ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 109
During the allocation process, when named resources are allocated to a plan, where is resource cost derived from?
Answer options
- A. Labor rate card for the user
- B. Labor rate card for the fiscal period
- C. Cost specified on the resource allocation
- D. Cost specified on user record
Correct answer: A
Explanation
The correct answer is A because the cost for the resource is derived from the labor rate card associated with the specific user. The other options do not accurately reflect the direct cost source as they refer to broader periods or different records that aren't specifically tied to the individual user.