Professional Scrum Product Owner I (PSPO I) — Question 8
Who is accountable for creating a valuable and usable Increment each Sprint? (Choose the best answer.)
Answer options
- A. The CEO.
- B. The Scrum Master.
- C. The Product Owner.
- D. The Scrum Team.
- E. The Developers.
Correct answer: E
Explanation
The correct answer is E, as the Developers are directly responsible for producing the Increment each Sprint. While the Scrum Master, Product Owner, and Scrum Team play important roles in the process, it is the Developers who actually create the Increment and ensure it meets the Definition of Done.