Professional Scrum Product Owner I (PSPO I) — Question 6
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Answer options
- A. The Sprint Goal.
- B. Sprint Review minutes.
- C. The Sprint Backlog.
- D. The release plan.
Correct answer: A
Explanation
The Sprint Goal serves as a clear target for the Development Team during the Sprint, guiding their efforts and priorities. In contrast, Sprint Review minutes are records of discussions, the Sprint Backlog is the list of tasks to be completed, and the release plan focuses on delivery schedules rather than immediate Sprint direction.