Professional Scrum Product Owner I (PSPO I) — Question 4

True or False: An Increment must be released to customers or users at the end of each Sprint.

Answer options

Correct answer: B

Explanation

The correct answer is False because while it is ideal to release an Increment at the end of a Sprint, it is not mandatory. A Sprint can end without a release if the team decides that the Increment is not ready for delivery or if the stakeholders do not require it.