Professional Scrum Master II (PSM II) — Question 89
Steven is a Scrum Master employed by the engineering department. The Director of Engineering considers using Scrum for a new project but wonders about the value of having all of the Development Team members attend the Daily Scrum. He is concerned that the employees already attend a lot of mandatory company meetings.
What are two outcomes of the Daily Scrum that Steven should explain on why the Daily Scrum is important? (Choose two.)
Answer options
- A. During the Daily Scrum the members of the Development Team will inform of problems that are hindering their progress, and for which they have no means to resolve. They will inform Steven as a Scrum Master, so he can remove the impediments and help the team be more productive.
- B. Through the short, daily alignment of the Daily Scrum the members of the Development Team grow and improve a shared understanding of the most important work to be undertaken in the next 24 hours to achieve the best possible progress toward the Sprint Goal. This daily opportunity to inspect and adapt will enable the Development Team to best tackle any unforeseen circumstances that might otherwise disrupt the team's progress.
- C. The Development Team members will produce a daily status report indicating how much time was spent working on individual tasks since the last Daily Scrum. The reports will help in discussing how the Sprint went at the Sprint Review meeting. It will provide detailed insights into the accuracy of estimates versus actual time spent, which can be used to create better estimates at the next Sprint Planning.
- D. The Daily Scrum serves for the Development Team to report to Steven, as a Scrum Master, all updates on the assigned tasks in the Sprint Backlog. He can then use the team's updates to plan their work for the next day, making sure that every team member is assigned the right tasks.
- E. During the Daily Scrum, the Development Team needs to update the Scrum board with their current status and progress, at a task level. This is crucial to ensure that the Directory of Engineering knows the team's actual progress and control the work being done.
Correct answer: A, B
Explanation
The correct answers, A and B, highlight the importance of communication and alignment among the Development Team members in identifying and addressing obstacles while ensuring progress towards the Sprint Goal. Options C, D, and E focus more on reporting and task assignments rather than the collaborative and adaptive nature of the Daily Scrum, which is not the primary purpose of this meeting.