Professional Scrum Master II (PSM II) — Question 87
Which statement is FALSE in regards to the Sprint Goal?
Answer options
- A. It is only a forecast and changes during the Sprint as more is learned.
- B. If it doesn't seem achievable, the Development Team has the courage to tell the Product Owner.
- C. The Product Owner respects the Development Team's opinion on whether they can achieve it.
- D. It helps increase focus.
- E. The Scrum Team discusses openly about alternative ways to reach it.
- F. The Development Team commits to it.
Correct answer: A
Explanation
The correct answer is A because the Sprint Goal is a fixed objective that provides focus for the team during the Sprint and should not change. Options B, C, D, E, and F are all true statements about the nature of the Sprint Goal and the responsibilities of the Scrum Team in relation to it.