Professional Scrum Master II (PSM II) — Question 82

The Development Team discovers that it doesn't have the tools and infrastructure to make each selected Product Backlog item done.
What is the most appropriate action for the Scrum Master to take?

Answer options

Correct answer: C

Explanation

The correct answer is C because the Scrum Master should facilitate the Development Team's growth and ensure that they have the necessary capabilities to meet their Definition of 'Done'. Option A is not advisable as stopping the Sprint disrupts the process, and Option B encourages accepting incomplete work, which is contrary to Scrum principles.