Professional Scrum Master II (PSM II) — Question 8
A new Product Owner has joined an existing Scrum Team that has been working together for eight Sprints. The Development Team has grown to have a good understanding of the functionality and business for the product they have been building. The Product Owner, being new to the company, is unsure about his responsibilities.
As a Scrum Master explain what two acceptable ways of helping the Product Owner would be. (Choose two.)
Answer options
- A. You advise the Product Owner to start building a good relationship with the stakeholders of the product. Ongoing interaction with them is important to regularly align with changing organizational or market expectations. The Product Owner is also expected to invite the right stakeholders to the Sprint Review meeting.
- B. You inform the Product Owner that, in today's highly competitive markets, it is important that the Development Team is updated on changing business priorities on a daily basis. The Daily Scrum allows the Development Team to adapt to the changes in scope without delay.
- C. You tell the Product Owner to make sure that there are no ambiguities or possible misunderstandings in the items on the Product Backlog when they are handed over to the Development Team. This is best done by capturing the functional requirements during an analysis phase, resulting in documents that are considered as the working product of such analysis Sprints.
- D. You advise the Product Owner to rely on the Development Team and the stakeholders to formulate the Product Backlog, as they are the ones most knowledgeable. By asking questions and working with them the Product Owner will quickly be up to speed.
Correct answer: A, D
Explanation
Option A is correct because building relationships with stakeholders is essential for a Product Owner to gather necessary feedback and align with expectations. Option D is also correct as it emphasizes the importance of collaboration with the Development Team and stakeholders in refining the Product Backlog. Options B and C are incorrect because they focus on daily updates and documentation processes, which are less critical in supporting the Product Owner's immediate understanding of their role.