Professional Scrum Master II (PSM II) — Question 71

Which approach would you recommend to ensure that the Product Backlog items discussed at Sprint Planning are well understood, actionable, and easier to forecast?

Answer options

Correct answer: D

Explanation

Option D is correct as it emphasizes collaboration between the Development Team and the Product Owner to ensure clarity and readiness of the top Product Backlog items. Option A is incorrect because it separates analysis from the Development Team, which can hinder understanding. Option B delays preparation, potentially causing confusion during Sprint Planning. Option C adds items during a Sprint, which may disrupt the team's focus and commitment.