Professional Scrum Master II (PSM II) — Question 64

During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint.
The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)

Answer options

Correct answer: A, D

Explanation

The correct responses are A and D because they focus on prioritizing the quality of the deliverables over merely measuring velocity, which aligns with Scrum principles. Option B, while supportive, does not address the need for quality improvement, and option C acknowledges the effort but lacks a proactive approach to enhancing quality.