Professional Scrum Master II (PSM II) — Question 58

A Scrum Team has been working on the same product for twelve Sprints. What would likely be the immediate impact on the original Scrum Team if two new
Scrum Teams are to be added the same product?

Answer options

Correct answer: A

Explanation

The introduction of two new Scrum Teams can create additional coordination and communication challenges, which can lead to a decrease in productivity for the original Scrum Team. While more teams might suggest a potential for increased output, the complexities of collaboration often outweigh the benefits in the short term. Therefore, the correct answer is A.