Professional Scrum Master II (PSM II) — Question 4

A new member has just joined an existing Development Team that has been together for several Sprints. During the Sprint, the individual has been trying to share his ideas and viewpoints but is continuously ignored by the rest of the Development Team.
Which three Scrum Values has the Development Team been neglecting? (Choose three.)

Answer options

Correct answer: B, E, F

Explanation

The Development Team has been neglecting Respect, Openness, and Courage by failing to acknowledge the new member's contributions. Respect is essential for fostering collaboration, Openness encourages sharing ideas, and Courage is necessary to voice opinions and challenge the status quo. The other values, although important, are not directly relevant to the scenario presented.