Professional Scrum Master II (PSM II) — Question 38
Peter, a Project Manager, has raised concerns about your Scrum Team's productivity and progress towards the objectives.
Which is the best way to respond to Peter's concerns?
Answer options
- A. Share the Product Backlog, the projections towards the release dates and ensure that Peter has access.
- B. Show the Profit & Loss (P&L) report.
- C. Share the current impediments.
- D. Share the last stakeholder status report prepared by the Scrum Master.
Correct answer: A
Explanation
The best way to alleviate Peter's concerns is to share the Product Backlog and release projections, as it directly relates to the team's productivity and progress. Option B, the Profit & Loss report, is not focused on project progress, while option C addresses impediments but does not provide a comprehensive view of productivity. Option D, the stakeholder status report, may not contain the detailed information Peter needs to understand the team's trajectory.