Professional Scrum Master II (PSM II) — Question 34

In order to start the first Sprint, Scrum only requires a Product Owner with enough ideas, a Development Team to execute on those ideas, and a Scrum Master to guide the process.

Answer options

Correct answer: B

Explanation

The correct answer is B because, in addition to the roles mentioned, Scrum also requires a well-defined Product Backlog that is prioritized and ready for the team to work on. Simply having the roles without a clear backlog does not fulfill the requirements to start the Sprint.