Professional Scrum Master II (PSM II) — Question 23
When multiple Scrum Teams are working from the same Product Backlog, also known as scaled Scrum, they must still work in conformance of the Scrum guide.
Answer options
- A. True
- B. False
Correct answer: A
Explanation
The correct answer is True because even in scaled Scrum, all teams must follow the principles and practices outlined in the Scrum guide. Option B is incorrect as it implies that the Scrum guide can be disregarded, which contradicts the framework's emphasis on maintaining its core values and rules.