Professional Scrum Master II (PSM II) — Question 2

In what two ways is velocity and technical debt related? (Choose two.)

Answer options

Correct answer: B, C

Explanation

Option B is correct because encountering technical debt during development can hinder progress and lower velocity. Option C is also correct as incurring technical debt can lead to a temporary increase in velocity, but this is unsustainable in the long run. Options A and D are incorrect because they misunderstand the relationship between technical debt and velocity.