Professional Scrum Master II (PSM II) — Question 191
What should a Development Team do with non-functional requirements?
Answer options
- A. Ensure they are addressed in every Increment.
- B. Assign them to the technical leads on the team.
- C. They will be addressed in the Integration Sprints.
- D. Add them to a separate non-functional requirements list.
Correct answer: A
Explanation
The correct answer is A because non-functional requirements need to be integrated into every Increment to ensure the product meets quality standards. Options B and D suggest delegating or isolating these requirements, which may lead to their neglect, while C implies they will only be handled during specific sprints, which is insufficient.