Professional Scrum Master II (PSM II) — Question 19

An organization wants to apply Scrum to build a new product and has hired Steven to be the Scrum Master of three new teams that will build the first release. The organization is new to Scrum and asks Steven for advice on how to start.
Which two things should Steven first advise? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers are B and D because having one Product Backlog ensures that all teams are aligned on the overall product vision and requirements, while a single Product Owner helps maintain focus on maximizing value and transparency. Options A and C are less effective as they could lead to misalignment and inefficiencies among the teams.