Professional Scrum Master II (PSM II) — Question 173
Scrum addresses which of the following four risks in software development? (Choose four.)
Answer options
- A. The complexity and unpredictability of the requirements.
- B. The stability and complexity of the technology.
- C. The skills and working relationships of the people on the teams.
- D. The timescale of the planned work.
- E. The clear definitions of stages and gateways in the overall governance model.
- F. The definition of incentive and bonus strategies by HR for all team members.
Correct answer: A, B, C, D
Explanation
Scrum focuses on managing complexities and uncertainties in requirements (A), technology (B), team dynamics (C), and project timelines (D), making these options correct. Options E and F do not directly relate to the core risks Scrum is designed to address in software development.