Professional Scrum Master II (PSM II) — Question 168
When does a Sprint end?
Answer options
- A. When there is no work remaining in the Sprint Backlog.
- B. When the time-box expires.
- C. It depends on the Product Owner.
- D. Immediately after the conclusion of the Sprint Review.
Correct answer: B
Explanation
The correct answer is B because a Sprint concludes when the time-box expires, which is a fundamental principle of Scrum. Option A is incorrect as the Sprint can end even if there are remaining tasks, while option C is misleading because the timing is not at the discretion of the Product Owner. Option D is also incorrect since the Sprint ends with the time-box, not immediately after the Sprint Review.