Professional Scrum Master II (PSM II) — Question 164
The Sprint length should be:
Answer options
- A. Short enough to keep the business risk acceptable to the Product Owner.
- B. Short enough to be able to synchronize the development work with other business events.
- C. No more than one month.
- D. All of these answers are correct.
Correct answer: D
Explanation
The correct answer is D because all the provided options highlight important aspects of Sprint length. A Sprint should indeed be short enough to manage business risk, synchronize with other events, and adhere to the one-month maximum guideline as per Scrum practices.