Professional Scrum Master II (PSM II) — Question 162
What must the Development Team do during the first Sprint?
Answer options
- A. Create a potentially shippable product Increment that includes at least one piece of functionality.
- B. Analyze and estimate the requirements for the subsequent Sprints.
- C. Create a project plan in order to map functional development to Sprint dates.
- D. Only design and develop the architecture and infrastructure.
Correct answer: A
Explanation
The correct answer is A, as the primary goal of the first Sprint is to produce a potentially shippable product Increment with at least one functional feature. Options B, C, and D are incorrect because they focus on planning and design rather than delivering a working product, which is the main focus of the initial Sprint.