Professional Scrum Master II (PSM II) — Question 156
How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?
Answer options
- A. Maximum of one day for Sprints that are time-boxed to two weeks.
- B. None. A new Sprint starts immediately following the conclusion of the previous Sprint.
- C. Enough time for the last Increment to finish testing.
- D. Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
- E. All of the above are allowed.
Correct answer: B
Explanation
The correct answer is B because, in Scrum, a new Sprint commences right after the previous one concludes without any breaks. Options A, C, D, and E are incorrect as they suggest delays or requirements that contradict the continuous flow of Sprints in the Scrum framework.