Professional Scrum Master II (PSM II) — Question 153
The Development Team can cancel the Sprint:
Answer options
- A. When the availability of the Product Owner is less than expected.
- B. When the requirements for the work to be done become unclear or not understood.
- C. It can't. Only Product Owners can cancel Sprints.
- D. When the Sprint Backlog is determined to be unachievable.
- E. When too many impediments occur.
Correct answer: C
Explanation
The correct answer is C because only the Product Owner has the authority to cancel a Sprint, regardless of the circumstances faced by the Development Team. Options A, B, D, and E present scenarios that may affect the Sprint but do not grant the Development Team the power to cancel it.