Professional Scrum Master II (PSM II) — Question 151

Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

Answer options

Correct answer: B

Explanation

The correct answer is B because multiple Scrum Teams can operate on different Sprint schedules even when they share a Product Backlog. This flexibility allows teams to manage their own workflows and deliver value independently, rather than being tied to a uniform Sprint start date.