Professional Scrum Master II (PSM II) — Question 15

Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new product to take 9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. The
Development Team is unsure if the required velocity is achievable.
What is the most effective way to recover?

Answer options

Correct answer: B

Explanation

The most effective way to recover is for the Development Team to communicate openly with Paul about the current state of progress and the unreleasability of the Increment. This ensures that the team addresses the existing issues before moving forward, allowing for accurate re-estimation and informed decision-making, which is not addressed by the other options.