Professional Scrum Master II (PSM II) — Question 149
What Product Owner activities occur between the end of the current Sprint and the beginning of the next Sprint?
Answer options
- A. Product Backlog refinement.
- B. Updating stakeholders on project progress.
- C. There are no such activities. When the current Sprint ends, the new Sprint begins.
- D. Participate as a team member at the Sprint Retrospective.
Correct answer: C
Explanation
The correct answer is C, as it indicates that there are no designated activities for the Product Owner during the gap between Sprints. The other options suggest ongoing tasks that might not be applicable during this transition phase, such as backlog refinement or stakeholder updates, which typically occur during Sprint cycles.