Professional Scrum Master II (PSM II) — Question 146

Who should manage the tasks of Development Team during the Sprint?

Answer options

Correct answer: D

Explanation

The Development Team is responsible for managing their own tasks during the Sprint, as they are self-organizing. The Project Manager, Product Owner, and Scrum Master have their own roles but do not dictate the tasks for the Development Team. Therefore, the correct answer is D.