Professional Scrum Master II (PSM II) — Question 138

Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?

Answer options

Correct answer: B

Explanation

The Development Team is responsible for managing the Sprint Backlog, including when updates are necessary based on their progress and insights. The Product Owner focuses on the product backlog and prioritization, while the Scrum Master facilitates the process and the Scrum Team encompasses all roles but does not specifically dictate updates to the backlog.