Professional Scrum Master II (PSM II) — Question 135

How should multiple Scrum Teams, working from the same Product Backlog, select the Product Backlog items their teams plan to work on?

Answer options

Correct answer: A

Explanation

The correct answer is A because it allows the Development Teams to choose items based on their capacity and expertise, while the Product Owner ensures that the most valuable work is presented. Options B, C, D, and E do not promote team autonomy or flexibility in selecting their work from a unified backlog.