Professional Scrum Master II (PSM II) — Question 133
What would be the responsibilities of a self-organizing Development Team?
Answer options
- A. Update stakeholders on the daily progress and keep the burn-down chart updated.
- B. Select the Product Backlog items for the Sprint and do the work planned in the Sprint Backlog.
- C. Writing User Stories and reordering the Product Backlog.
- D. Deciding on the value of the product features and value estimations.
Correct answer: B
Explanation
The correct answer, B, is accurate because a self-organizing Development Team is responsible for selecting which items from the Product Backlog to work on during a Sprint and for completing the tasks in the Sprint Backlog. Options A, C, and D do not correctly represent the core responsibilities of the Development Team in the context of Scrum, as they focus on communication, creation of User Stories, and value decisions, which are not their primary duties.