Professional Scrum Master II (PSM II) — Question 129
Who should be present to review and adjust the selected Sprint work if the Development Team determines that it will not be able to finish the complete forecast?
Answer options
- A. The stakeholders and Scrum Master.
- B. The Product Owner and the Development Team.
- C. The Development Team and Project Manager.
- D. The Scrum Master, the Business Analyst and the Development Team.
Correct answer: B
Explanation
The correct answer is B because the Product Owner is responsible for the product backlog and must collaborate with the Development Team to adjust their commitments. The other options include roles not directly responsible for making adjustments to the Sprint's work, such as the Project Manager or stakeholders, who are not part of the Scrum framework.