Professional Scrum Master II (PSM II) — Question 119
Who is responsible for ensuring the Product Backlog items are understood to the level needed?
Answer options
- A. The Business Analyst.
- B. The Scrum Master.
- C. The Development Team.
- D. The Product Owner.
Correct answer: D
Explanation
The Product Owner is responsible for ensuring that the Product Backlog items are clearly understood by the team, as they prioritize and define the items. The other roles, such as the Business Analyst, Scrum Master, and Development Team, have different responsibilities and do not hold the accountability for the clarity of the Product Backlog items.