Professional Scrum Master II (PSM II) — Question 116
Which of these tools is mandatory for the Product Owner to use?
Answer options
- A. Release burnup chart.
- B. Burndown chart.
- C. Version control.
- D. Project Gantt chart.
- E. None of the above.
Correct answer: E
Explanation
The correct answer is E, as there are no tools that are strictly mandatory for the Product Owner. While tools like the burndown chart or Gantt chart can be beneficial, they are not required. Each team can adopt tools that best fit their workflow.