Professional Scrum Master II (PSM II) — Question 108
Which of the following is true about the Product Owner role?
Answer options
- A. Can be shared between multiple people on a Scrum Team, Is the same as a Project Manager. Is played by a committee or a team of people.
- B. Is one person. Can be influenced by a committee. Is accountable for ordering the Product Backlog.
Correct answer: B
Explanation
The correct answer is B because the Product Owner is indeed a single person who is accountable for managing the Product Backlog. Option A is incorrect as it misrepresents the role by suggesting it can be shared or performed by a group, which contradicts the definition of the Product Owner.