Professional Scrum Master II (PSM II) — Question 106
Which of the following actions is appropriate for a Scrum Master at the Daily Scrum?
Answer options
- A. Making sure each member has an opportunity to answer all three questions.
- B. Leading the Daily Scrum.
- C. Teaching the Development Team to keep the Daily Scrum time-boxed to 15 minutes or less.
- D. Updating the Scrum board.
- E. All of the above.
Correct answer: C
Explanation
The correct answer is C because the Scrum Master should educate the Development Team on maintaining the time-box for the Daily Scrum. Option A is incorrect as not every member is required to answer all questions. Option B is also wrong because the Daily Scrum is not led by the Scrum Master, but rather the team members. Option D is not the Scrum Master's role, and option E is incorrect as not all actions listed are appropriate.