Professional Scrum Master II (PSM II) — Question 106

Which of the following actions is appropriate for a Scrum Master at the Daily Scrum?

Answer options

Correct answer: C

Explanation

The correct answer is C because the Scrum Master should educate the Development Team on maintaining the time-box for the Daily Scrum. Option A is incorrect as not every member is required to answer all questions. Option B is also wrong because the Daily Scrum is not led by the Scrum Master, but rather the team members. Option D is not the Scrum Master's role, and option E is incorrect as not all actions listed are appropriate.