Professional Scrum Master II (PSM II) — Question 103

During Sprint Planning, the Development Team was not able to confidently forecast a Sprint Backlog but the Scrum Team was able to create a Sprint Goal for upcoming Sprint. What action should the Scrum Master take?

Answer options

Correct answer: C

Explanation

The correct answer is C because it focuses on addressing the issue by proactively forecasting the necessary items and planning to discuss the challenges in the Sprint Retrospective. Options A and B do not resolve the situation effectively and could lead to unnecessary delays. Option D does not directly address the Development Team's inability to forecast and may not provide a solution to the root cause of the problem.