Professional Scrum Master I (PSM I) — Question 94

Who should make sure everyone on the Scrum Team does his or her tasks for the Sprint?

Answer options

Correct answer: D

Explanation

The Scrum Team as a whole is accountable for managing their own tasks and ensuring that they meet their commitments for the Sprint. While the Project Manager, Product Owner, and Scrum Master play supportive roles, they do not directly oversee the team's task completion. Therefore, the correct answer is D, as it emphasizes the collective responsibility of the Scrum Team.