Professional Scrum Master I (PSM I) — Question 91
What enhances the transparency of an Increment? (Choose the best answer.)
Answer options
- A. Doing all work needed to meet the Definition of Done.
- B. Updating Sprint tasks properly in the electronic tracking tool.
- C. Keeping track of and estimating all undone work to be completed in a 'hardening' Sprint.
- D. Reporting Sprint progress to the stakeholders daily.
Correct answer: A
Explanation
The correct answer is A because meeting the Definition of Done ensures that the Increment is fully complete and functional, thereby increasing transparency. Option B, while important for tracking, does not directly contribute to the overall completeness of the Increment. Option C focuses on future work rather than the current Increment's transparency, and option D, although useful for communication, does not enhance the actual quality or completeness of the Increment itself.