Professional Scrum Master I (PSM I) — Question 69
When must the Product Owner participate in the Daily Scrum?
Answer options
- A. When the Product Owner needs to represent the stakeholders' point of view to the Developers.
- B. When there are impediments to discuss.
- C. When the Scrum Master asks the Product Owner to attend.
- D. When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer.
Correct answer: D
Explanation
The correct answer is D because the Product Owner should only participate in the Daily Scrum when they are directly involved in the work being done, acting as a Developer. Options A, B, and C are incorrect as they do not define mandatory attendance based on active involvement in Sprint Backlog tasks.