Professional Scrum Master I (PSM I) — Question 67
When is it most appropriate for a Development Team to change the definition of `Done`?
Answer options
- A. During Spring Planning.
- B. Prior to starting a new Sprint.
- C. During the Sprint Retrospective.
- D. Prior to starting a new project.
Correct answer: C
Explanation
The definition of `Done` should be evaluated and potentially altered during the Sprint Retrospective, which is a time for the team to reflect on their processes. Changing it during Sprint Planning or before a new Sprint may not allow for the necessary reflection on past experiences, while modifying it before a new project lacks the context of previous work.