Professional Scrum Master I (PSM I) — Question 65
Which two things should the Scrum Team do during the first Sprint? (Choose two.)
Answer options
- A. Make up a plan for the rest of the project.
- B. Define the major product features and a release plan architecture.
- C. Build at least one piece of valuable functionality.
- D. Analyze, describe, and document the requirements for the subsequent Sprints.
- E. Create at least one valuable, useful Increment.
Correct answer: C, E
Explanation
The correct answers, C and E, focus on delivering functional value in the first Sprint, which is essential for Scrum. Options A and B are not appropriate as they involve planning for the future rather than executing on immediate deliverables. Option D, while important, pertains to future Sprints and does not align with the immediate goals of the first Sprint.