Professional Scrum Master I (PSM I) — Question 6
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)
Answer options
- A. Recruit additional Development Team members before the work can begin.
- B. The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.
- C. Cancel the Sprint.
- D. Remove or change selected Product Backlog items.
- E. The Development Team works overtime during this Sprint.
Correct answer: B, D
Explanation
The correct actions are B and D. Option B is valid because informing the Product Owner and proceeding with monitoring allows the team to adjust as needed. Option D is also correct as modifying the Product Backlog can help align the workload with their capacity. Options A, C, and E are not suitable; recruiting new members mid-Sprint is impractical, canceling the Sprint is extreme, and working overtime may lead to burnout.