As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct actions are B and D. Option B is valid because informing the Product Owner and proceeding with monitoring allows the team to adjust as needed. Option D is also correct as modifying the Product Backlog can help align the workload with their capacity. Options A, C, and E are not suitable; recruiting new members mid-Sprint is impractical, canceling the Sprint is extreme, and working overtime may lead to burnout.