Which of these may a Development Team deliver at the end of a Sprint?

Answer options

Correct answer: C

Explanation

The correct answer is C because it reflects the Scrum principle of delivering potentially shippable product increments that meet the Definition of Done. Options A and B do not represent completed deliverables, and D, while possibly deliverable, does not align with the primary goal of delivering a functional increment of software.