Professional Scrum Master I (PSM I) — Question 45
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
Answer options
- A. Run the Daily Scrum.
- B. Prioritize the Development Team's work on the Sprint Backlog.
- C. Update management on what is being worked on.
- D. Answer questions from the Development Team about items in the current Sprint.
Correct answer: C, D
Explanation
The correct answers are C and D because the Product Owner is responsible for communicating progress to management and clarifying any questions the Development Team has about the Sprint. Options A and B are incorrect as running the Daily Scrum is primarily the Scrum Master’s role, and prioritizing tasks on the Sprint Backlog is not typically the Product Owner's responsibility during the Sprint.