Professional Scrum Master I (PSM I) — Question 43
Which three purposes does the definition of `Done` serve? (Choose three.)
Answer options
- A. Guide the Development Team on how many Product Backlog items to select for the Sprint.
- B. Create a shared understanding of when work is complete.
- C. Describe the purpose, objective, and time-box of each Scrum event.
- D. Describe the work that must be done before the Sprint is allowed to end.
- E. Increase transparency.
Correct answer: A, B, E
Explanation
The correct answers, A, B, and E, highlight the role of the definition of `Done` in guiding the Development Team, fostering a shared understanding of completion, and promoting transparency. Options C and D do not align with the purposes of the definition of `Done`, as they pertain to Scrum events and specific Sprint requirements rather than the completion criteria.