Professional Scrum Master I (PSM I) — Question 40
Which of the following is required by Scrum?
Answer options
- A. Sprint Retrospective.
- B. Members must be stand up at the Daily Scrum.
- C. Sprint Burndown Chart.
- D. Release planning.
- E. All of the above.
Correct answer: A
Explanation
The Sprint Retrospective is a required event in Scrum that allows the team to reflect on their process and improve. While the Daily Scrum and other elements are important practices, they are not mandated in the same way as the Sprint Retrospective. Therefore, options B, C, D, and E are not correct as they do not represent required components of Scrum.